Auction Factory Checklist: Power, Floor Loading and CCC Before You Bid

Crispina Ng·Published 14 Nov 2026·Updated 15 Nov 2026·By property type
Auction Factory Checklist: Power, Floor Loading and CCC Before You Bid

You usually cannot walk inside a factory before the auction. The Proclamation of Sale gives an address, a title, a land area and a reserve price, but rarely the power supply, floor loading, clear height, the licences the last occupier held, or whether the building has a Certificate of Completion and Compliance (CCC). This checklist shows what you can check from outside sources before you bid, what stays unknown until handover, and what happens to the previous Manufacturing Licence, TNB account, pollution and illegal extensions once the factory is yours.

Key Takeaways

  • All 2,132 Proclamations of Sale BidNest has read sell the property as it is, where it is: you take the factory with its defects, missing approvals, extensions and occupants, and each lot's Conditions of Sale decide the details (BidNest market report).
  • Only the principal submitting person can issue a CCC, and occupying a building without one is an offence under the Street, Drainage and Building Act 1974. Factories approved before 12 April 2007 may have a council Certificate of Fitness instead.
  • The land use category ("industry", "building" or "agriculture") and the express conditions are endorsed on the title under the National Land Code: an official search shows both.
  • A Manufacturing Licence is issued to the manufacturer for each place of manufacturing activity and cannot be transferred without the licensing officer's prior approval, so plan your own licence or exemption with MIDA.
  • Electricity is not inherited: you apply to TNB as the new owner (the Proclamation of Sale is accepted as proof of ownership). Illegal extensions and pollution notices land on the owner, so price them into your bid.

Why a factory auction needs more homework

A factory must work for a specific use: enough electricity, a floor that carries the machines, height for racking, and approvals to operate. In BidNest's sample of RM400,000+ auctions in Kuala Lumpur, Selangor, Negeri Sembilan and Putrajaya, 100% of Proclamations use as-is terms, so the checks happen before auction day. These shares describe the auctions BidNest lists, not every auction in Malaysia. For the process itself, start with the BidNest lelong buying guide; terms are explained in the glossary.

1. Title and land use

Run a title search (Selangor steps: e-Tanah Selangor title search; Kuala Lumpur: e-Tanah KL title search) and check:

  1. Category of land use. Section 52 of the National Land Code sets three categories, "agriculture", "building" and "industry", endorsed on the title. Under section 117, "industry" land must be used for industrial purposes such as factories, workshops and warehouses.
  2. Express conditions. They can narrow the permitted use. Changing them needs the proprietor's application to the State Authority under section 124.
  3. Consents and tenure. Of the Proclamations BidNest has read, 58.9% require the State Authority's consent and 47.2% are leasehold: check the remaining lease.
  4. Type of sale. 78.9% are bank sales by assignment (LACA), 19.5% court-ordered sales and 1.5% bank sales of a charged title. See LACA vs non-LACA auctions.

Zoning under the local plan is a separate question: ask the council's planning department.

How do you check the industrial title deed of an auction factory?

Apply to the land registry or land office for an official search under section 385 of the National Land Code. The certificate of search names the registered proprietor, summarises entries still in force, states the express conditions and restrictions in interest, and shows dealings, caveats or prohibitory orders presented. Check the category reads "industry" and the conditions fit your use.

A private search under section 384 lets you inspect the register yourself for a fee. In a LACA sale there may be only a master title or no title yet, so also read the Proclamation for the developer's and the State Authority's consents, and check for registered caveats as in checking a factory's bank charge and caveat.

2. CCC or Certificate of Fitness

The Street, Drainage and Building (Amendment) Act 2007 took effect on 12 April 2007 and replaced the council's Certificate of Fitness for Occupation with the CCC; projects approved earlier kept receiving Certificates of Fitness. Under section 70 of Act 133:

  • only the principal submitting person (the architect, engineer or building draftsman who submitted the plans) may issue a CCC, after ensuring the building follows the approved plans, meets the council's technical conditions and is safe and fit for occupation;
  • occupying, or permitting the occupation of, a building without a CCC carries a fine of up to RM250,000, jail of up to 10 years, or both.

The CCC is Form F, backed by Forms G1 to G21, and the services confirmed for it include the TNB supply, water, sewerage and, where applicable, Bomba clearance for active fire-fighting systems.

Before bidding: ask the auctioneer or the bank's solicitors whether a copy of the CCC or Certificate of Fitness is on file, ask the council's building department what it can confirm, and look for extensions or mezzanines that may not be in the approval. FactoryHub, a factory listing site, explains what a CCC is and why it matters when buying a factory.

What should you do if an auction factory has illegal extensions?

Treat an unapproved extension, mezzanine or roofed yard as your problem after the sale. Under section 72 of Act 133 the council serves its demolition notice on the owner of the land, and section 70(11) fines alterations made without permission up to RM25,000 with a possible court order to alter or demolish. Budget to regularise or remove it.

Practical steps:

  1. Before bidding, compare what you see from the road with the council's approved plans, if the council will show them, and with the floor area on the title or Proclamation.
  2. Price two outcomes: regularising the extension (section 70(14) lets plans be submitted late through a principal submitting person, with a fee of five to twenty times the prescribed fee) or demolishing it.
  3. Do not rent it out as it is. Section 73(3) makes letting an unauthorised building an offence, with a fine of up to RM1,000.
  4. Ask the council whether any notice is already outstanding on the lot.

More on who answers for past works in lelong property illegal renovation.

3. Power supply (TNB)

TNB supplies at low voltage (230V, 400V), medium voltage (6.6kV to 33kV) or high voltage (132kV, 275kV), and its connection charge is based on the customer's declared maximum demand. More load means an upgrade application to TNB. From outside you can look for a substation or transformer on or beside the lot and compare with similar factories in the same park, whose listings often state power capacity. The declared maximum demand and the switchboards' condition are only certain after handover. Proclamation arrears terms usually cover quit rent, assessment and maintenance, not utility bills, so ask the auctioneer about unpaid electricity and water, and see unpaid water and electricity bills on a lelong property.

Does an auction factory need to reapply for TNB electricity?

Yes. The previous owner's or tenant's account does not pass to you, so you open your own account with TNB. TNB's business page lists the Proclamation of Sale as accepted proof of ownership and, for commercial or industrial premises, asks for a development order, permit, licence or other local authority approval. Charges and deposit are paid upfront.

What TNB's page says for business applicants:

Item What TNB asks
Load up to 100A An electrical contractor registered with the Energy Commission (an existing premise may apply without one if the service cable, meter board and wiring are in good condition and unchanged)
Load above 100A An electrical consultant engineer registered with the Board of Engineers Malaysia applies for you
Company applicant Signed form, authorisation letter on letterhead, SSM registration documents, ID of the authorised person
Proof of ownership Land title or latest title search, stamped SPA, or the complete Proclamation of Sale
Industrial premises Development order, permit, licence or other approval from the local authority
Payment Connection charges, stamp duty and security deposit upfront

TNB also advises having the internal wiring inspected by a registered electrical contractor when you do not know its condition. For the full move-in list, see after buying an auction property.

4. Floor loading and clear height

These are design figures in the structural drawings, which the owner holds. To estimate them, look for the industrial park's original sales brochure, compare listings of the same building type in the park, and check what is visible from the road: roof height, loading bays and lorry access. If your machines need a specific floor loading, keep a budget for an engineer's assessment after handover.

5. Bomba and the Department of Environment

Section 28 of the Fire Services Act 1988 requires a fire certificate, renewable annually, for designated premises; the owner, occupier or manager applies and Bomba inspects first. Under the Environmental Quality Act 1974, using prescribed premises without a licence is an offence (section 18), a new occupier must apply to transfer an existing licence (section 14), and converting premises into prescribed premises needs prior written permission (section 19).

What should you do if an auction factory has environmental pollution issues?

Find out before you bid, because the Department of Environment can act against the owner as well as the occupier. Section 31 of the Environmental Quality Act 1974 lets the Director General order the owner or occupier of premises to install control equipment, study the risk, monitor, or remove and dispose of pollution, within a set time.

What you can do from outside: look for drums, sludge, stained drains or abandoned tanks visible from the road, ask the auctioneer what the last occupier manufactured, and check with the Department of Environment's state office whether any notice or licence is recorded for the address. After handover, an environmental assessment by a qualified consultant tells you what clean-up costs. Machinery and waste left inside are covered in is the machinery included in an auction factory.

6. Licences to operate

Can an auction factory continue to use the previous Manufacturing Licence?

Not automatically. Under the Industrial Co-ordination Act 1975, a Manufacturing Licence is issued to the manufacturer, with a separate licence for each place of manufacturing activity, and section 7 forbids transfer without the licensing officer's prior approval. Buying the factory gives you the building, not the seller's licence: apply to MIDA for your own.

MIDA's 2024 guideline says a licence is needed by manufacturers with shareholders' funds of RM2.5 million and above or 75 or more full-time paid employees; smaller companies can apply for an exemption. Section 7(2) lets the officer authorise a transfer in cases such as the holder's liquidation or the appointment of a receiver, which is a matter for the licence holder, not the auction buyer. The council's business licence and the DOE and Bomba approvals are separate: check each with the issuing body.

What you cannot know until handover

Interior condition, roof leaks, wiring and fire systems, machinery left behind, the original plans, and whether anyone is still inside. Getting the factory empty is your job: see vacant possession after an auction, and arrange insurance before you get the keys.

Put the unknowns into your price

Compare the reserve with the open market as in auction factory vs market price in Selangor, deduct a budget for the unknowns (CCC, extensions, power upgrade, clean-up), and run the outlay through the auction cost calculator. In BidNest's sample, 71.8% of Proclamations ask for a 10% deposit and 28.2% for 5%; 58% allow 90 days for the balance and 42% allow 120 days. Each unsold round usually lowers the reserve by about 10%. Browse auction factories and warehouses, including lots in Shah Alam and Klang.

This article is general information, not legal or financial advice.

Pollution and illegal extensions at an auction factory

What should you do if an auction factory has environmental pollution issues?

Ask what the last occupier made, look for visible waste, and check with the Department of Environment before bidding. Under section 31 of the Environmental Quality Act 1974 the Director General can order the owner or occupier to remove or mitigate pollution, so budget for an assessment and clean-up.

What should you do if an auction factory has illegal extensions?

Price them in before you bid. The council can serve a demolition notice on the land owner under section 72 of Act 133, and unapproved alterations carry fines and possible court orders to alter or demolish. You can regularise through a principal submitting person at a higher fee, or remove the structure.

For help with auction dates, reserve prices and financing on an auction factory, contact Crispina Ng, a lelong property specialist with 12 years in bank auctions and a former banker.

Sources:

Frequently Asked Questions

Also answered in full elsewhere on BidNest: Who pays outstanding bills on an auction factory?.

Can I view an auction factory before bidding?

Usually only from outside. All 2,132 Proclamations of Sale BidNest has read sell the property as it is, where it is, and the borrower or a tenant may still occupy it. Plan your checks assuming you will not get inside.

How do I check if an auction factory has a CCC?

Ask the auctioneer or the bank's solicitors for a copy of the CCC (or, for older buildings, the Certificate of Fitness), and ask the local council's building department what it can confirm. Only the principal submitting person can issue a CCC under section 70 of Act 133. Later extensions may not be covered.

What happens if the factory I win has no CCC?

Occupying or permitting the occupation of a building without a CCC is an offence under Act 133, with a fine of up to RM250,000, jail of up to 10 years, or both. You would need professionals to regularise the building before use, so price that cost and delay into your bid.

How do I find out the power supply of an auction factory?

Look for a substation or transformer and compare with similar factories in the same park. TNB's connection charge is based on declared maximum demand, and more load needs an upgrade application. The exact capacity is only certain after handover.

Does the fire certificate transfer to the new owner?

The Fire Services Act 1988 requires a fire certificate for designated premises, renewable annually, applied for by the owner, occupier or manager after a Bomba inspection. Plan to apply for your own use rather than rely on the previous one.

Can an auction factory continue to use the previous Manufacturing Licence?

No. The licence belongs to the manufacturer and its place of manufacturing activity, and the Industrial Co-ordination Act 1975 bars transfer without the licensing officer's prior approval. If your company meets MIDA's thresholds (RM2.5 million shareholders' funds or 75 full-time employees), apply for your own licence or an exemption.

How do you check the industrial title deed of an auction factory?

Get an official search from the land registry or land office under section 385 of the National Land Code. It shows the proprietor, the express conditions and restrictions, and entries such as caveats or prohibitory orders. Confirm the land use category is "industry" and that the conditions allow your activity.

Does an auction factory need to reapply for TNB electricity?

Yes, you apply for your own account. TNB accepts the complete Proclamation of Sale as proof of ownership, asks for local authority approval for industrial premises, and needs a registered electrical consultant engineer for loads above 100A. Connection charges, stamp duty and the deposit are paid upfront.

Contact Crispina Ng

Speak to Crispina Ng for the latest auction details, reserve price and bidding process. About BidNest and its data